|
The Stages of Construction |
|
July 7
August 10
August 16
October 6, 2009 |
 |
|
April 17, 2009 |
 |
|
Photo Below: Wednesday, April 29, 2009 |
 |
|
Photo Below:
Friday, May 8, 2009, 5:45 P.M. |
 |
 |
|
Friday, July 3, 2009
The panels arrived on July 3, 2009 |
 |
|
Tuesday, July 7, 2009
Below are the Polly Steel Panel
(walls) being assembled and erected |
 |
 |
 |
 |
 |
 |
|

|
 |
 |
 |
 |
|
Sunday, July 12,
2009 |
 |
 |
|
Monday, July 20, 2009
Pouring of the walls |
 |
 |
 |
|
|
|
|
|
Photos Below was
Taken July 24, 2009 |
 |
 |
|
|
|
Photos Below was
Taken August 2, 2009 |
 |
 |
 |
|
Photos Below Were Taken on Monday, August 10, 2009 |
 |
 |
 |
|
Photo Below Was
Taken Thursday, August 13, 2009 |
 |
 |
|
Photo Below Was Taken Sunday, August 16, 2009 |
 |
|
Below: September
7, 2009. Windows being installed. Fiberglass
installation, electrical, plumbing, sheet rock. |
 |
|
|
|
Photos below were
taken October 6, 2009 |
 |
 |
 |
 |
 |
 |
 |
|

|
 |
 |
|
|
|
January 18, 2010: No
work was done on the house for two months. A new contractor
will complete the house. |
|
March, 2, 2010: No work was done
on the house for four months
A new contract to complete the house was
signed by Duane Moxey (license contractor).
The goal is to complete the house within six
weeks. |
|
Below: The house is
at the same stage on March 3, 2010 as it was on October 6, 2009 |
 |
-
Construction began April 17, 2009
-
We received occupancy certificate on
Tuesday, July 6, 2010
-
We paid for electricity on Thursday, July 8,
2010 after getting electrical approval that same day.
-
We moved in the house July 22,
2010 with no electricity. This is fifteen months from the
first day construction began (460 days). However, the
outside of the home was not yet completed when we moved in.
The outside walls were not completed with bonded seal.
-
Electricity was turned on July
28, 2010.
-
Cable Bahamas television turned
on August 30, 2010
-
Cable Bahamas Internet turned on
August 31, 2010
-
Telephone was turned on August 31, 2010
|
|
|